Project Name: New Madrid Customer: Associated Electric Cooperative Inc.
Location: New Madrid, Missouri Equipment: 650 MW H2 cooled BBC Generators
Week 4/18 - 4/24/2005 Week 4/25 - 5/1/2005 Week 5/2 - 5/8/2005 Week 5/9 - 5/15/2005

May 21, 2005
The generator is done. I'm hitting the road.
Thanks for your interest in my site and this outage.

May 21, 2005
Installing the mouse trap on the HP cross over connection

May 20, 2005
Going back together after figuring out where the leak was. Darrel is lowering upper triple seal housing into the generator.

May 20, 2005
Cross over pipes installed on HP and being torqued down

May 19, 2005
DE H2 seal housing removed for leak investigation

May 19, 2005
Heating and tightening HP casing flange bolts

May 18, 2005
Continuing tightening coupling coupling bolts on the LP2-Gen coupling
Still looking for leaks on the generator. Turbine is still repairing HP casing flange

May 17, 2005
Weld repair on HP outer casing flange in progress

May 17, 2005
Rear end of generator slowly taking shape

May 16, 2005
Well here's at least one picture from the other night.
Aligning the outboard slip ring brush bracket.