Project Name: Leibstadt Customer: KKL Leibstadt
Location: Leibstadt, Switzerland Equipment: 1200 MW H2 cooled BBC Generator
My latest assignment brought me to a nuclear plant in Leibstadt, Switzerland.
After a core failure the generator was completely dismantled and repairs were carried out during 5 months.
I was asked to join the repair and re-assembly efforts.
Below some pictures from the media.

Here's the generator in assembled condition.

The generator dismantled for inspection.

Removing of the stator winding.

View of the core

In the front are the removed stator bar wile in the back you can see the stator housing with the end casing removed.

View onto the NDE press plate mounted at the end of the core. Installation of the temperature sensors on the press plate.